GDS Shanghai SH13 Jiading
GDS · Jiading SH13
- IT live
- 12 MW
- Free to lease
- 0.8 MW
- $ / kW·mo
- $91
- White space
- 114k ft²
Inventory
93% occupiedPower
12 MWlive
0.8 MW to lease · 11.2 MW in use
White space
114k ft²total
4,773 ft² free · 109k ft² occupied
11k m² · 443 m² free
Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.
Power
About 8 MW of the utility feed is cooling, conversion, and house load.
Power cost
$91/kW·mo
9.7¢ industrial · 12.4¢ after PUE 1.28
- Per MW·year
- $1.1M
- This site · 12 MW
- $13M/yr
- 12 kW rack
- $1,088/mo
3.0× the cheapest market (Iceland Landsvirkjun). Same IT load there is $8.7M/yr less.
Shanghai industrial 35 kV+ · utility tariff × PUE, not colo list price.
- Redundancy
- N+1
- Opened
- 2021
- Renewable match
- 30%
- Rack density
- 12 kW
- PUE
- 1.281.00 ideal · 1.60 typical
- Power source
- State Grid Shanghai. Dual 10-110 kV feeds. Waigaoqiao / Zhangjiang / Minhang belt.
Cooling
Plant
Hybrid
Liquid
Deployed
Rack density
12 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.
Network carriers
4On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
5Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Shanghai, Shanghai, China
Jiading District, Shanghai
31.375°, 121.252° · Asia
Tenants / users
Hyperscale, cloud, enterprise — Alibaba, Tencent, AWS China, Azure China
Notes
SH13 Jiading. Northwest Shanghai DR and enterprise overflow from Pudong. Smaller converted hall, not the Waigaoqiao flagship.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.