Verne Iceland Campus
Verne · Keflavík
- IT live
- 90 MW
- Free to lease
- 48.5 MW
- $ / kW·mo
- $26
- White space
- 180k ft²
Inventory
46% occupiedPower
90 MWlive
48.5 MW to lease · 41.5 MW in use
White space
180k ft²total
97k ft² free · 83k ft² occupied
17k m² · 9,012 m² free
Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.
Power
About 85 MW of the utility feed is cooling, conversion, and house load.
Power cost
$26/kW·mo
3.3¢ industrial · 3.6¢ after PUE 1.10
- Per MW·year
- $318k
- This site · 90 MW
- $29M/yr
- 80 kW rack
- $2,120/mo
cheapest in the index (Iceland Landsvirkjun). Same IT load there is $867k/yr less.
Iceland Landsvirkjun · utility tariff × PUE, not colo list price.
- Redundancy
- N+1
- Opened
- 2012
- Renewable match
- 100%
- Rack density
- 80 kW
- PUE
- 1.101.00 ideal · 1.60 typical
- Power source
- Landsvirkjun 100% hydro/geothermal. 40-acre campus. Nvidia DGX-ready.
Cooling
Plant
Direct-to-chip
Liquid
Deployed
Rack density
80 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
First liquid-cooled deployment on campus for Nscale: 15 MW, 4,600 Blackwell Ultra (85% liquid). Free-air for the rest.
Network carriers
4On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
2Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Keflavík, Southern Peninsula, Iceland
Keflavík / former NATO base, Iceland
63.985°, -22.605° · Europe
Tenants / users
Nscale, HPC, enterprise
Notes
Ardian-owned. 140 MW IT capacity. Nscale's first Iceland GPU cluster completed phase 1 in three months (April 2026).
Compiled from public filings, operator pages, and reporting. Not an official operator specification.