Under construction
Colocation
Liquid cooling
Tier III

Vantage Frontier Texas

Vantage Data Centers · TX12 Frontier

Vantage Frontier Texas facility
Vantage Data Centers · Source
Planned IT
1.4 GW
Free to lease
1.1 GW
$ / kW·mo
$58
White space
2.8M ft²

Inventory

20% occupied

Power

1.4 GWlive

1.1 GW to lease · 280 MW in use

White space

2.8M ft²total

2.2M ft² free · 560k ft² occupied

260k m² · 208k m² free

Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.

Power

IT live—
Free to lease1.1 GW
Utility feed—
Campus / planned1.4 GW

Power cost

$58/kW·mo

6.6¢ industrial · 7.9¢ after PUE 1.20

Per MW·year
$694k
This site · 1.4 GW
$971M/yr
80 kW rack
$4,625/mo
3.2¢ cheapdear 22.4¢

2.1× the cheapest market (Iceland Landsvirkjun). Same IT load there is $500M/yr less.

ERCOT industrial · utility tariff × PUE, not colo list price.

Redundancy
2N
Opened
2027
Renewable match
40%
Rack density
80 kW
PUE
1.201.00 ideal · 1.60 typical
Power source
ERCOT West.

Cooling

Plant

Hybrid

Liquid

Deployed

Rack density

80 kW

H100-eq

—

WUE

—

Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.

Liquid-ready wholesale halls for hyperscale AI deployments.

Network carriers

6

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

4

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Albany, Texas, United States

Shackelford County, TX (near Albany; Highways 604 and 351)

32.728°, -99.295° · North America

Tenants / users

Hyperscale tenants (undisclosed)

Notes

Vantage Frontier campus targeting 1.4 GW in West Texas.

Operator site

Compiled from public filings, operator pages, and reporting. Not an official operator specification.