Start Campus SIN01
Start Campus / Nscale · Sines Data Campus
- IT live
- 31 MW
- Remaining
- 0 MW
- $ / kW·mo
- $87
- White space
- 62k ft²
Inventory
100% occupiedPower
31 MWcampus
0 MW to commission · 31 MW in use
White space
62k ft²total
— free · 62k ft² occupied
5,760 m²
Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.
Power
About 7.8 MW of the utility feed is cooling, conversion, and house load.
Power cost
$87/kW·mo
10.8¢ industrial · 11.9¢ after PUE 1.10
- Per MW·year
- $1M
- This site · 31 MW
- $32M/yr
- 80 kW rack
- $6,938/mo
3.4× the cheapest market (Iceland Landsvirkjun). Same IT load there is $23M/yr less.
Portugal Sines / Start Campus · utility tariff × PUE, not colo list price.
- Redundancy
- 2N
- Opened
- 2025
- Renewable match
- 100%
- Rack density
- 80 kW
- PUE
- 1.101.00 ideal · 1.60 typical
- Power source
- Portuguese grid plus 100% renewable PPAs. Former coal-plant interconnection at Sines.
Cooling
Plant
Seawater
Liquid
Deployed
Rack density
80 kW
H100-eq
32k
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Seawater heat rejection from the Atlantic plus direct-to-chip on GB300 NVL72. Target WUE of 0 — no freshwater towers.
Network carriers
4On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
2Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Sines, Setúbal, Portugal
SINES Data Campus, Sines, Portugal
37.956°, -8.870° · Europe
Tenants / users
Microsoft, Nscale
Notes
First building of Europe's largest permitted coastal AI campus. 12,600 Nvidia Blackwell Ultra GPUs for Microsoft. Ocean cooling, PUE 1.1.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.