Project Thunderbird
Plainsmen Holdings · Project Thunderbird data center and power corridor
- Planned IT
- 2.8 GW
- Free to lease
- —
- $ / kW·mo
- $61
- White space
- —
Inventory
100% occupiedPower
2.8 GWlive
0 MW to lease · 2.8 GW in use
White space
—total
— free
—
Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.
Power
Power cost
$61/kW·mo
6.4¢ industrial · 8.3¢ after PUE —
- Per MW·year
- $729k
- This site · 2.8 GW
- $2B/yr
2.0× the cheapest market (Iceland Landsvirkjun). Same IT load there is $1B/yr less.
Oklahoma industrial · utility tariff × PUE, not colo list price.
- Redundancy
- —
- Opened
- —
- Renewable match
- —
- Rack density
- —
- Voltage
- —
- PUE
- —1.00 ideal · 1.60 typical
- Power source
- On-site natural gas generation (up to 3.3 GW, proposed)
Cooling
Plant
Air / CRAH
Liquid
Not deployed
Rack density
—
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Cooling design not published by the operator for this site; typed air as the neutral default.
Network carriers
0No on-net carriers published.
On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
0No public-cloud on-ramp published.
Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Enid, Oklahoma, United States
36.396°, -97.878° · North America
Notes
Enid City Commission approved three rezonings 6-1 on Oct 27 2026 covering the North (560 ac, proposed site of an up to 3.3 GW on-site gas power plant) and West (305 ac) campuses of Plainsmen Holdings' proposed four-campus, about 1,735-acre corridor; developer states up to 2.75 GW of IT capacity at full build. Rezoning does not approve a data center: an intensive-use review is still required and no operator has been selected. Coordinates: Enid city center (approximate). Sources: https://www.enidnews.com/news/business/commission-approves-rezoning-requests-for-project-thunderbird/article_ec2057f2-6911-4d68-b32f-8539f100c67d.html https://projectthunderbird.com/ https://www.enid.org/Home/Information-Hub/Development/Thunderbird
Compiled from public filings, operator pages, and reporting. Not an official operator specification.