Oracle Cloud Turin
Oracle · eu-turin-1
- IT live
- 8 MW
- Remaining
- 8 MW
- $ / kW·mo
- $148
- White space
- 96k ft²
Inventory
50% occupiedPower
16 MWcampus
8 MW to commission · 8 MW in use
White space
192k ft²total
96k ft² free · 96k ft² occupied
18k m² · 8,933 m² free
Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.
Power
About 12 MW of the utility feed is cooling, conversion, and house load.
Power cost
$148/kW·mo
17.6¢ industrial · 20.2¢ after PUE 1.15
- Per MW·year
- $1.8M
- This site · 8 MW
- $14M/yr
- 16 kW rack
- $2,364/mo
5.5× the cheapest market (Iceland Landsvirkjun). Same IT load there is $12M/yr less.
Italy industrial / Piedmont · utility tariff × PUE, not colo list price.
- Redundancy
- N+1
- Opened
- 2023
- Renewable match
- 55%
- Rack density
- 16 kW
- PUE
- 1.151.00 ideal · 1.60 typical
- Power source
- Terna / Enel. Dual MV inlets plus on-site diesel. Gas-marginal Italian grid.
Cooling
Plant
Hybrid
Liquid
Deployed
Rack density
16 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.
Network carriers
6On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
1Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Turin, Piedmont, Italy
Greater Turin (AZ undisclosed)
45.078°, 7.682° · Europe
Tenants / users
Oracle Cloud
Notes
OCI Italy North. Pair to Google europe-west12 and Noovle on the Turin belt.