Operational
Hyperscale
Liquid cooling
Tier III

Oracle Cloud Osaka

Oracle · Osaka

IT live
12 MW
Remaining
6 MW
$ / kW·mo
$144
White space
54k ft²

Inventory

67% occupied

Power

18 MWcampus

6 MW to commission · 12 MW in use

White space

80k ft²total

27k ft² free · 54k ft² occupied

7,465 m² · 2,488 m² free

Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.

Power

IT live12 MW
Remaining6 MW
Utility feed22.5 MW
Campus / planned18 MW

About 10.5 MW of the utility feed is cooling, conversion, and house load.

Power cost

$144/kW·mo

16.2¢ industrial · 19.8¢ after PUE 1.22

Per MW·year
$1.7M
This site · 12 MW
$21M/yr
18 kW rack
$2,597/mo
3.2¢ cheapdear 22.4¢

5.1× the cheapest market (Iceland Landsvirkjun). Same IT load there is $17M/yr less.

Kansai Electric · utility tariff × PUE, not colo list price.

Redundancy
N+1
Opened
2020
Renewable match
50%
Rack density
18 kW
PUE
1.221.00 ideal · 1.60 typical
Power source
Kansai Electric (KEPCO). Dual feeds. Seismically isolated building.

Cooling

Plant

Hybrid

Liquid

Deployed

Rack density

18 kW

H100-eq

WUE

Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.

Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.

Network carriers

6

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

1

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Osaka, Osaka, Japan

Osaka region

34.705°, 135.505° · Asia

Tenants / users

Oracle Cloud, DR for Tokyo

Notes

OCI Osaka region.

Operator site

Compiled from public filings, operator pages, and reporting. Not an official operator specification.