Oracle Cloud Osaka
Oracle · Osaka
- IT live
- 12 MW
- Remaining
- 6 MW
- $ / kW·mo
- $144
- White space
- 54k ft²
Inventory
67% occupiedPower
18 MWcampus
6 MW to commission · 12 MW in use
White space
80k ft²total
27k ft² free · 54k ft² occupied
7,465 m² · 2,488 m² free
Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.
Power
About 10.5 MW of the utility feed is cooling, conversion, and house load.
Power cost
$144/kW·mo
16.2¢ industrial · 19.8¢ after PUE 1.22
- Per MW·year
- $1.7M
- This site · 12 MW
- $21M/yr
- 18 kW rack
- $2,597/mo
5.1× the cheapest market (Iceland Landsvirkjun). Same IT load there is $17M/yr less.
Kansai Electric · utility tariff × PUE, not colo list price.
- Redundancy
- N+1
- Opened
- 2020
- Renewable match
- 50%
- Rack density
- 18 kW
- PUE
- 1.221.00 ideal · 1.60 typical
- Power source
- Kansai Electric (KEPCO). Dual feeds. Seismically isolated building.
Cooling
Plant
Hybrid
Liquid
Deployed
Rack density
18 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.
Network carriers
6On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
1Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Osaka, Osaka, Japan
Osaka region
34.705°, 135.505° · Asia
Tenants / users
Oracle Cloud, DR for Tokyo
Notes
OCI Osaka region.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.