Oracle Cloud Montréal

Oracle · ca-montreal-1

IT live
16 MW
Remaining
8 MW
$ / kW·mo
$42
White space
134k ft²

Inventory

67% occupied

Power

24 MWcampus

8 MW to commission · 16 MW in use

White space

201k ft²total

67k ft² free · 134k ft² occupied

19k m² · 6,221 m² free

Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.

Power

IT live16 MW
Remaining8 MW
Utility feed30 MW
Campus / planned24 MW

About 14 MW of the utility feed is cooling, conversion, and house load.

Power cost

$42/kW·mo

5¢ industrial · 5.7¢ after PUE 1.14

Per MW·year
$499k
This site · 16 MW
$8M/yr
18 kW rack
$749/mo
3.2¢ cheapdear 22.4¢

1.6× the cheapest market (Iceland Landsvirkjun). Same IT load there is $2.9M/yr less.

Hydro-Québec Rate L · utility tariff × PUE, not colo list price.

Redundancy
N+1
Opened
2020
Renewable match
99%
Rack density
18 kW
PUE
1.141.00 ideal · 1.60 typical
Power source
Hydro-Québec. Dual MV inlets plus on-site diesel. ~99.8 percent hydro (Rate L on large sites).

Cooling

Plant

Hybrid

Liquid

Deployed

Rack density

18 kW

H100-eq

—

WUE

—

Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.

Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.

Network carriers

7

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

1

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Montréal, Quebec, Canada

Greater Montréal (AZ undisclosed)

45.510°, -73.570° · North America

Tenants / users

Oracle Cloud

Notes

OCI Canada Southeast. Dual-site with Toronto. Hydro-Québec.

Operator site

Compiled from public filings, operator pages, and reporting. Not an official operator specification.