Oracle Cloud Milan
Oracle · eu-milan-1
- IT live
- 16 MW
- Remaining
- 8 MW
- $ / kW·mo
- $156
- White space
- 134k ft²
Inventory
67% occupiedPower
24 MWcampus
8 MW to commission · 16 MW in use
White space
201k ft²total
67k ft² free · 134k ft² occupied
19k m² · 6,221 m² free
Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.
Power
About 14 MW of the utility feed is cooling, conversion, and house load.
Power cost
$156/kW·mo
18.6¢ industrial · 21.4¢ after PUE 1.15
- Per MW·year
- $1.9M
- This site · 16 MW
- $30M/yr
- 18 kW rack
- $2,811/mo
5.8× the cheapest market (Iceland Landsvirkjun). Same IT load there is $25M/yr less.
Italy industrial / Milan · utility tariff × PUE, not colo list price.
- Redundancy
- N+1
- Opened
- 2021
- Renewable match
- 50%
- Rack density
- 18 kW
- PUE
- 1.151.00 ideal · 1.60 typical
- Power source
- Terna / Enel. Dual MV inlets plus on-site diesel. Gas-marginal Italian grid.
Cooling
Plant
Hybrid
Liquid
Deployed
Rack density
18 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.
Network carriers
6On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
1Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Milan, Lombardy, Italy
Greater Milan (AZ undisclosed)
45.472°, 9.176° · Europe
Tenants / users
Oracle Cloud
Notes
OCI Italy Northwest. Dual-site with Turin.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.