Oracle Cloud Marseille

Oracle · eu-marseille-1

IT live
12 MW
Remaining
6 MW
$ / kW·mo
$90
White space
108k ft²

Inventory

67% occupied

Power

18 MWcampus

6 MW to commission · 12 MW in use

White space

162k ft²total

54k ft² free · 108k ft² occupied

15k m² · 5,025 m² free

Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.

Power

IT live12 MW
Remaining6 MW
Utility feed22.5 MW
Campus / planned18 MW

About 10.5 MW of the utility feed is cooling, conversion, and house load.

Power cost

$90/kW·mo

10.6¢ industrial · 12.3¢ after PUE 1.16

Per MW·year
$1.1M
This site · 12 MW
$13M/yr
16 kW rack
$1,436/mo
3.2¢ cheapdear 22.4¢

3.3× the cheapest market (Iceland Landsvirkjun). Same IT load there is $9M/yr less.

France Enedis / Marseille · utility tariff × PUE, not colo list price.

Redundancy
N+1
Opened
2021
Renewable match
85%
Rack density
16 kW
Voltage
PUE
1.161.00 ideal · 1.60 typical
Power source
RTE / Enedis. Dual MV inlets plus on-site diesel. Nuclear-heavy French grid (ARENH).

Cooling

Plant

Hybrid

Liquid

Deployed

Rack density

16 kW

H100-eq

—

WUE

—

Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.

Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.

Network carriers

6

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

1

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Marseille, Provence-Alpes-Côte d'Azur, France

Greater Marseille (AZ undisclosed)

43.310°, 5.380° · Europe

Tenants / users

Oracle Cloud

Notes

OCI France South. Pair to Interxion MRS for subsea and Maghreb latency.

Operator site

Compiled from public filings, operator pages, and reporting. Not an official operator specification.