ODATA QR04 San Miguel
ODATA (Aligned) · QR04
- IT live
- 12 MW
- Free to lease
- 1.4 MW
- $ / kW·mo
- $95
- White space
- 125k ft²
Inventory
88% occupiedPower
12 MWlive
1.4 MW to lease · 10.6 MW in use
White space
125k ft²total
6,000 ft² free · 119k ft² occupied
12k m² · 557 m² free
Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.
Power
About 18 MW of the utility feed is cooling, conversion, and house load.
Power cost
$95/kW·mo
10.2¢ industrial · 13.1¢ after PUE 1.28
- Per MW·year
- $1.1M
- This site · 12 MW
- $14M/yr
- 20 kW rack
- $1,906/mo
3.2× the cheapest market (Iceland Landsvirkjun). Same IT load there is $9.4M/yr less.
CFE industrial · utility tariff × PUE, not colo list price.
- Redundancy
- 2N
- Opened
- 2025
- Renewable match
- 30%
- Rack density
- 20 kW
- PUE
- 1.281.00 ideal · 1.60 typical
- Power source
- CFE. Dual 23 kV or 115 kV inlets plus on-site diesel. Mexican federal grid; interconnection queues are the constraint.
Cooling
Plant
Hybrid
Liquid
Deployed
Rack density
20 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.
Network carriers
5On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
4Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
San Miguel de Allende, Guanajuato, Mexico
Near San Miguel de Allende, Guanajuato
20.914°, -100.744° · North America
Tenants / users
Hyperscale, cloud
Notes
Opened Aug 2025. 12 MW initial of 24 MW design. Guanajuato overflow from power-constrained Queretaro.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.