Operational
Colocation
Air cooled
Tier III

NXDATA-1 Bucharest

NXDATA · Pipera

IT live
2.5 MW
Free to lease
0.3 MW
$ / kW·mo
$114
White space
24k ft²

Inventory

86% occupied

Power

2.5 MWlive

0.3 MW to lease · 2.1 MW in use

White space

24k ft²total

2,734 ft² free · 21k ft² occupied

2,250 m² · 254 m² free

Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.

Power

IT live2.5 MW
Free to lease0.3 MW
Utility feed3.1 MW
Campus / planned2.5 MW

About 0.6 MW of the utility feed is cooling, conversion, and house load.

Power cost

$114/kW·mo

11.8¢ industrial · 15.6¢ after PUE 1.32

Per MW·year
$1.4M
This site · 2.5 MW
$3.4M/yr
6 kW rack
$682/mo
3.2¢ cheapdear 22.4¢

3.7× the cheapest market (Iceland Landsvirkjun). Same IT load there is $2.5M/yr less.

OPCOM · utility tariff × PUE, not colo list price.

Redundancy
N+1
Opened
2002
Renewable match
55%
Rack density
6 kW
Voltage
PUE
1.321.00 ideal · 1.60 typical
Power source
Transelectrica. Dual 20 kV inlets. Nuclear (Cernavoda), hydro, and wind mix.

Cooling

Plant

Air / CRAH

Liquid

Not deployed

Rack density

6 kW

H100-eq

WUE

Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.

Chilled-water CRAH, N+1. Isolated hot aisles. Not an AI factory unless noted.

Network carriers

4

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

4

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Bucharest, Bucharest, Romania

8 Dimitrie Pompeiu Boulevard, Feper Building, Sector 2

44.480°, 26.118° · Europe

Tenants / users

Networks, enterprise, RoNIX

Notes

First carrier-neutral hall in Romania (2002). Former Feper factory, Pipera. Interconnection, not wholesale AI.

Operator site

Compiled from public filings, operator pages, and reporting. Not an official operator specification.