NTT NAV7 Airoli
NTT GDC · NAV Airoli
- IT live
- 36 MW
- Free to lease
- 23.3 MW
- $ / kW·mo
- $93
- White space
- 113k ft²
Inventory
35% occupiedPower
36 MWlive
23.3 MW to lease · 12.7 MW in use
White space
113k ft²total
73k ft² free · 40k ft² occupied
10k m² · 6,759 m² free
Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.
Power
About 39 MW of the utility feed is cooling, conversion, and house load.
Power cost
$93/kW·mo
10.2¢ industrial · 12.8¢ after PUE 1.25
- Per MW·year
- $1.1M
- This site · 36 MW
- $40M/yr
- 30 kW rack
- $2,792/mo
3.2× the cheapest market (Iceland Landsvirkjun). Same IT load there is $28M/yr less.
MSEDCL · utility tariff × PUE, not colo list price.
- Redundancy
- 2N
- Opened
- 2024
- Renewable match
- 30%
- Rack density
- 30 kW
- PUE
- 1.251.00 ideal · 1.60 typical
- Power source
- MSEDCL / Tata Power plus on-site generators. Dual utility feeds where available.
Cooling
Plant
Hybrid
Liquid
Deployed
Rack density
30 kW
H100-eq
—
WUE
0.72 L/kWh
fleet avg · 2024 · 227k m³/yr at 36 MW
Operator fleet average applied to this hall — not a site meter. NTT DATA GDC 2025 Sustainability Report (FY2024).
Direct-to-chip cold plates and rear-door heat exchangers. Designed for GB200/Blackwell-class racks.
Network carriers
6On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
5Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Navi Mumbai, Maharashtra, India
Airoli, Navi Mumbai
19.162°, 73.006° · Asia
Tenants / users
Hyperscale, AI, cloud
Notes
Newest NAV hall. Campus master plan toward 200 MW+ across seven buildings.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.