Naver Gak Chuncheon
Naver Cloud · Chuncheon
- IT live
- 40 MW
- Remaining
- 20 MW
- $ / kW·mo
- $93
- White space
- 167k ft²
Inventory
67% occupiedPower
60 MWcampus
20 MW to commission · 40 MW in use
White space
250k ft²total
83k ft² free · 167k ft² occupied
23k m² · 7,742 m² free
Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.
Power
About 35 MW of the utility feed is cooling, conversion, and house load.
Power cost
$93/kW·mo
10.6¢ industrial · 12.7¢ after PUE 1.20
- Per MW·year
- $1.1M
- This site · 40 MW
- $45M/yr
- 20 kW rack
- $1,857/mo
3.3× the cheapest market (Iceland Landsvirkjun). Same IT load there is $31M/yr less.
KEPCO industrial · utility tariff × PUE, not colo list price.
- Redundancy
- N+1
- Opened
- 2013
- Renewable match
- 40%
- Rack density
- 20 kW
- PUE
- 1.201.00 ideal · 1.60 typical
- Power source
- KEPCO. Dual utility feeds.
Cooling
Plant
Free air
Liquid
Deployed
Rack density
20 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Gangwon free-air economization plus liquid loops on AI halls. Named 각 (Gak).
Network carriers
4On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
5Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Chuncheon, Gangwon, South Korea
Chuncheon, Gangwon
37.881°, 127.730° · Asia
Tenants / users
Naver, NAVER Cloud
Notes
Naver's first purpose-built DC. Cool-climate Gangwon campus.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.