Planned
Hyperscale
Air cooled

Microsoft Person County

Microsoft Azure

Planned IT
—
Remaining
—
$ / kW·mo
$73
White space
—

Power

IT live—
Remaining—
Utility feed—
Campus / planned—

Power cost

$73/kW·mo

7.7¢ industrial · 10¢ after PUE —

Per MW·year
$877k
This site
—
3.2¢ cheapdear 22.4¢

2.4× the cheapest market (Iceland Landsvirkjun).

Duke Energy · utility tariff × PUE, not colo list price.

Redundancy
—
Opened
—
Renewable match
—
Rack density
—
Voltage
—
PUE
—1.00 ideal · 1.60 typical
Power source
—

Cooling

Plant

Air / CRAH

Liquid

Not deployed

Rack density

—

H100-eq

—

WUE

0.27 L/kWh

fleet avg · 2025

0 dry2.50 evaporative

Operator fleet average applied to this hall — not a site meter. Microsoft FY2025 water intensity disclosure.

Cooling design not published by the operator for this site; typed air as the neutral default.

Network carriers

0

No on-net carriers published.

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

1

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Person County, North Carolina, United States

36.397°, -78.988° · North America

Tenants / users

Microsoft

Notes

Microsoft Local (official community page): Microsoft is planning to build datacenters in Catawba County and Person County, North Carolina. Capacity, investment and building count not published there. Coordinates: OSM relation 2528733 (county center, approximate). Source: https://local.microsoft.com/communities/americas/north-carolina/

Operator site

Compiled from public filings, operator pages, and reporting. Not an official operator specification.