Microsoft East Wenatchee
Microsoft Azure
- Planned IT
- —
- Remaining
- —
- $ / kW·mo
- $70
- White space
- —
Power
Power cost
$70/kW·mo
7.4¢ industrial · 9.6¢ after PUE —
- Per MW·year
- $843k
- This site
- —
2.3× the cheapest market (Iceland Landsvirkjun).
SCL / PSE · utility tariff × PUE, not colo list price.
- Redundancy
- —
- Opened
- —
- Renewable match
- —
- Rack density
- —
- Voltage
- —
- PUE
- —1.00 ideal · 1.60 typical
- Power source
- —
Cooling
Plant
Air / CRAH
Liquid
Not deployed
Rack density
—
H100-eq
—
WUE
0.27 L/kWh
fleet avg · 2025
Operator fleet average applied to this hall — not a site meter. Microsoft FY2025 water intensity disclosure.
Cooling design not published by the operator for this site; typed air as the neutral default.
Network carriers
0No on-net carriers published.
On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
1Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
East Wenatchee, Washington, United States
Douglas County, Washington
47.419°, -120.211° · North America
Tenants / users
Microsoft
Notes
Microsoft Local (official community page): Microsoft is developing new datacenters in Malaga and East Wenatchee; typed planned (no stage given). Capacity, investment and building count not published there. Coordinates: OSM way 1309105917 (facility outline). Source: https://local.microsoft.com/communities/americas/quincy/
Compiled from public filings, operator pages, and reporting. Not an official operator specification.