Operational
Hyperscale
Liquid cooling
Tier III

Microsoft Chile Central

Microsoft Azure · Santiago

IT live
50 MW
Remaining
0 MW
$ / kW·mo
$76
White space
179k ft²

Inventory

100% occupied

Power

50 MWcampus

0 MW to commission · 50 MW in use

White space

179k ft²total

free · 179k ft² occupied

17k m²

Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.

Power

IT live50 MW
Remaining0 MW
Utility feed62.5 MW
Campus / planned50 MW

About 12.5 MW of the utility feed is cooling, conversion, and house load.

Power cost

$76/kW·mo

industrial · 10.3¢ after PUE 1.15

Per MW·year
$907k
This site · 50 MW
$45M/yr
25 kW rack
$1,889/mo
3.2¢ cheapdear 22.4¢

2.8× the cheapest market (Iceland Landsvirkjun). Same IT load there is $29M/yr less.

Chile SIC · utility tariff × PUE, not colo list price.

Redundancy
N+1
Opened
2024
Renewable match
95%
Rack density
25 kW
PUE
1.151.00 ideal · 1.60 typical
Power source
Chile hydro/solar.

Cooling

Plant

Hybrid

Liquid

Deployed

Rack density

25 kW

H100-eq

WUE

0.27 L/kWh

fleet avg · 2025 · 118k m³/yr at 50 MW

0 dry2.50 evaporative

Operator fleet average applied to this hall — not a site meter. Microsoft FY2025 water intensity disclosure.

Hybrid plus liquid-ready AI halls.

Network carriers

5

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

1

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Santiago, Santiago Metropolitan, Chile

Santiago Metropolitan Region

-33.450°, -70.680° · South America

Tenants / users

Azure

Notes

Microsoft Chile Central region.

Operator site

Compiled from public filings, operator pages, and reporting. Not an official operator specification.