Planned
Hyperscale
Air cooled

Meta Mason County

Meta · Mason County hyperscale campus

Planned IT
—
Remaining
—
$ / kW·mo
$76
White space
—

Power

IT live—
Remaining—
Utility feed—
Campus / planned—

Power cost

$76/kW·mo

8¢ industrial · 10.4¢ after PUE —

Per MW·year
$911k
This site
—
3.2¢ cheapdear 22.4¢

2.5× the cheapest market (Iceland Landsvirkjun).

US industrial · utility tariff × PUE, not colo list price.

Redundancy
—
Opened
—
Renewable match
—
Rack density
—
Voltage
—
PUE
—1.00 ideal · 1.60 typical
Power source
—

Cooling

Plant

Air / CRAH

Liquid

Not deployed

Rack density

—

H100-eq

—

WUE

0.18 L/kWh

fleet avg · 2023

0 dry2.50 evaporative

Operator fleet average applied to this hall — not a site meter. Meta fleet (0014 convention).

Cooling design not published by the operator for this site; typed air as the neutral default.

Network carriers

0

No on-net carriers published.

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

0

No public-cloud on-ramp published.

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Maysville, Kentucky, United States

38.641°, -83.744° · North America

Tenants / users

Meta

Notes

Mason County Fiscal Court unanimously approved a resolution to proceed with a hyperscale data center contracting with Meta on Oct 13 2026; more than 2,000 acres zoned, initial investment about USD 15B per the county's attorney, 40-year multi-phase plan, initial construction expected within three years. Capacity not published. Coordinates: Maysville town center (approximate). Source: https://www.wkyt.com/2026/10/14/mason-county-approves-hyperscale-data-center-deal-with-meta/

Operator site

Compiled from public filings, operator pages, and reporting. Not an official operator specification.