Operational
Hyperscale
Air cooled

Meta Clonee

Meta

Planned IT
—
Remaining
—
$ / kW·mo
$165
White space
—

Power

IT live—
Remaining—
Utility feed—
Campus / planned—

Power cost

$165/kW·mo

17.4¢ industrial · 22.6¢ after PUE —

Per MW·year
$2M
This site
—
3.2¢ cheapdear 22.4¢

5.4× the cheapest market (Iceland Landsvirkjun).

Ireland industrial · utility tariff × PUE, not colo list price.

Redundancy
—
Opened
—
Renewable match
100%
Rack density
—
Voltage
—
PUE
—1.00 ideal · 1.60 typical
Power source
Irish grid. Meta-supported wind and solar projects in Ireland add 219 MW; electricity matched 100% with clean and renewable energy (Meta).

Cooling

Plant

Air / CRAH

Liquid

Not deployed

Rack density

—

H100-eq

—

WUE

0.18 L/kWh

fleet avg · 2023

0 dry2.50 evaporative

Operator fleet average applied to this hall — not a site meter. Meta 2023 Sustainability Report.

Cooling design not published on Meta's info sheet; typed air as the neutral default.

Network carriers

0

No on-net carriers published.

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

0

No public-cloud on-ramp published.

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Clonee, County Meath, Ireland

Dunboyne / Clonee, County Meath

53.417°, -6.430° · Europe

Tenants / users

Meta

Notes

Broke ground 2016; investment EUR 1.4B (Meta). Operational per Meta's info sheet. Capacity not published. Coordinates: OSM relation 16056528 (facility footprint). Sources: https://datacenters.atmeta.com/all-locations/ ; https://datacenters.atmeta.com/asset/clonee-data-center-info-sheet/

Operator site

Compiled from public filings, operator pages, and reporting. Not an official operator specification.