Layer 9 Queretaro
Layer 9 Data Centers · QRO
- Planned IT
- 24 MW
- Free to lease
- 24 MW
- $ / kW·mo
- $89
- White space
- 100k ft²
Inventory
0% occupiedPower
24 MWlive
24 MW to lease · 0 MW in use
White space
100k ft²total
100k ft² free · — occupied
9,290 m² · 9,290 m² free
Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.
Power
Power cost
$89/kW·mo
9.8¢ industrial · 12.3¢ after PUE 1.25
- Per MW·year
- $1.1M
- This site · 24 MW
- $26M/yr
- 20 kW rack
- $1,789/mo
3.1× the cheapest market (Iceland Landsvirkjun). Same IT load there is $17M/yr less.
CFE Queretaro · utility tariff × PUE, not colo list price.
- Redundancy
- 2N
- Opened
- 2027
- Renewable match
- 30%
- Rack density
- 20 kW
- PUE
- 1.251.00 ideal · 1.60 typical
- Power source
- CFE. Dual 23 kV or 115 kV inlets plus on-site diesel. Mexican federal grid; interconnection queues are the constraint.
Cooling
Plant
Hybrid
Liquid
Deployed
Rack density
20 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.
Network carriers
6On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
4Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Queretaro, Queretaro, Mexico
Queretaro
20.572°, -100.368° · North America
Tenants / users
Hyperscale, cloud, enterprise
Notes
New-entrant Mexican wholesale. Arizton lists Layer 9 among 2025-26 Queretaro builders. Construction.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.