Under construction
Colocation
Liquid cooling
Tier III

IXcellerate MOS11 Veshki

IXcellerate · Veshki

Planned IT
130 MW
Free to lease
130 MW
$ / kW·mo
$50
White space
464k ft²

Inventory

0% occupied

Power

130 MWlive

130 MW to lease · 0 MW in use

White space

464k ft²total

464k ft² free · occupied

43k m² · 43k m² free

Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.

Power

IT live
Free to lease130 MW
Utility feed
Campus / planned130 MW

Power cost

$50/kW·mo

5.6¢ industrial · 6.8¢ after PUE 1.22

Per MW·year
$598k
This site · 130 MW
$78M/yr
25 kW rack
$1,247/mo
3.2¢ cheapdear 22.4¢

1.7× the cheapest market (Iceland Landsvirkjun). Same IT load there is $33M/yr less.

Mosenergosbyt · utility tariff × PUE, not colo list price.

Redundancy
N+1
Opened
2026
Renewable match
18%
Rack density
25 kW
PUE
1.221.00 ideal · 1.60 typical
Power source
MOESK / Mosenergosbyt. Dual 10 kV inlets plus on-site diesel. Gas-heavy Moscow grid; nuclear from Rosenergoatom on the ring.

Cooling

Plant

Hybrid

Liquid

Deployed

Rack density

25 kW

H100-eq

WUE

Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.

High-density to 55 kW per rack without hall redesign. Cold-wall containment. Direct-to-chip options for AI cabinets.

Network carriers

6

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

4

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Veshki, Moscow Oblast, Russia

Veshki, Moscow Oblast

55.926°, 37.608° · Europe

Tenants / users

Cloud, wholesale, AI pipeline

Notes

Third IXcellerate campus. 130 MW design. First 600 racks targeted summer 2026. CNews: the only operator still launching ~2,000 racks a year through 2025-26.

Operator site

Compiled from public filings, operator pages, and reporting. Not an official operator specification.