IREN Mackenzie
IREN · Mackenzie
- IT live
- 80 MW
- Remaining
- 0 MW
- $ / kW·mo
- $44
- White space
- 417k ft²
Inventory
100% occupiedPower
80 MWcampus
0 MW to commission · 80 MW in use
White space
417k ft²total
— free · 417k ft² occupied
39k m²
Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.
Power
About 20 MW of the utility feed is cooling, conversion, and house load.
Power cost
$44/kW·mo
5.8¢ industrial · 6.1¢ after PUE 1.05
- Per MW·year
- $533k
- This site · 80 MW
- $43M/yr
- 20 kW rack
- $889/mo
1.8× the cheapest market (Iceland Landsvirkjun). Same IT load there is $19M/yr less.
BC Hydro Peace / Kootenay · utility tariff × PUE, not colo list price.
- Redundancy
- N+1
- Opened
- 2020
- Renewable match
- 98%
- Rack density
- 20 kW
- PUE
- 1.051.00 ideal · 1.60 typical
- Power source
- BC Hydro interior 138/230 kV. Dual feeds. Mackenzie / Peace hydro.
Cooling
Plant
Free air
Liquid
Not deployed
Rack density
20 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Cool-climate free-air economization most of the year. Closed-loop dry coolers; no evaporative towers.
Network carriers
6On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
4Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Mackenzie, British Columbia, Canada
Mackenzie, BC
55.333°, -123.094° · North America
Tenants / users
Bitcoin self-mining, IREN Cloud overflow
Notes
Peace-region hydro. Part of IREN's 160 MW Canadian book (Mackenzie, Prince George, Canal Flats). Canadian expansion slowing as Childress TX 750 MW takes the AI contract.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.