Google Canelones
Google · Parque de las Ciencias

- Planned IT
- 56 MW
- Remaining
- 56 MW
- $ / kW·mo
- $82
- White space
- 140k ft²
Inventory
0% occupiedPower
56 MWcampus
56 MW pipeline · 0 MW in use
White space
140k ft²total
140k ft² free · — occupied
13k m² · 13k m² free
Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.
Power
Power cost
$82/kW·mo
10¢ industrial · 11.2¢ after PUE 1.12
- Per MW·year
- $981k
- This site · 56 MW
- $55M/yr
- 40 kW rack
- $3,270/mo
3.1× the cheapest market (Iceland Landsvirkjun). Same IT load there is $37M/yr less.
UTE · utility tariff × PUE, not colo list price.
- Redundancy
- 2N
- Opened
- 2027
- Renewable match
- 95%
- Rack density
- 40 kW
- PUE
- 1.121.00 ideal · 1.60 typical
- Power source
- Uruguayan grid — already ~98% renewable (wind/hydro/solar). US$850m campus.
Cooling
Plant
Closed-loop liquid
Liquid
Deployed
Rack density
40 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Closed-loop liquid after community water objections forced a net-positive water pledge.
Network carriers
3On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
1Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Canelones, Canelones, Uruguay
Camino de los Horneros, Parque de las Ciencias, Canelones
-34.750°, -56.000° · South America
Tenants / users
Google Cloud
Notes
Google's Uruguay AI hub. Completes in phases through 2028. Set a regional precedent on water.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.