Google Cloud Paris
Google · europe-west9
- IT live
- 48 MW
- Remaining
- 32 MW
- $ / kW·mo
- $84
- White space
- 357k ft²
Inventory
60% occupiedPower
80 MWcampus
32 MW to commission · 48 MW in use
White space
595k ft²total
238k ft² free · 357k ft² occupied
55k m² · 22k m² free
Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.
Power
About 52 MW of the utility feed is cooling, conversion, and house load.
Power cost
$84/kW·mo
10.4¢ industrial · 11.4¢ after PUE 1.10
- Per MW·year
- $1M
- This site · 48 MW
- $48M/yr
- 25 kW rack
- $2,088/mo
3.3× the cheapest market (Iceland Landsvirkjun). Same IT load there is $33M/yr less.
France Enedis / Ile-de-France · utility tariff × PUE, not colo list price.
- Redundancy
- N+1
- Opened
- 2022
- Renewable match
- 96%
- Rack density
- 25 kW
- PUE
- 1.101.00 ideal · 1.60 typical
- Power source
- RTE / Enedis. Dual MV inlets plus on-site diesel. Nuclear-heavy French grid (ARENH).
Cooling
Plant
Hybrid
Liquid
Deployed
Rack density
25 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.
Network carriers
6On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
1Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Paris, Île-de-France, France
Greater Paris (AZ undisclosed)
48.840°, 2.280° · Europe
Tenants / users
Google Cloud
Notes
europe-west9. Three zones. 96 percent CFE matching on the French nuclear-plus-renewable mix. Not St. Ghislain (Belgium, europe-west1).
Compiled from public filings, operator pages, and reporting. Not an official operator specification.