Operational
Colocation
Air cooled
Tier III

Equinix TR4

Equinix · Toronto

IT live
10 MW
Free to lease
1.3 MW
$ / kW·mo
$106
White space
83k ft²

Inventory

87% occupied

Power

10 MWlive

1.3 MW to lease · 8.7 MW in use

White space

83k ft²total

11k ft² free · 73k ft² occupied

7,742 m² · 1,006 m² free

Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.

Power

IT live10 MW
Free to lease1.3 MW
Utility feed13 MW
Campus / planned10 MW

About 3 MW of the utility feed is cooling, conversion, and house load.

Power cost

$106/kW·mo

10.6¢ industrial · 14.5¢ after PUE 1.37

Per MW·year
$1.3M
This site · 10 MW
$13M/yr
5 kW rack
$530/mo
3.2¢ cheapdear 22.4¢

3.3× the cheapest market (Iceland Landsvirkjun). Same IT load there is $8.9M/yr less.

Toronto Hydro / IESO · utility tariff × PUE, not colo list price.

Redundancy
N+1
Opened
2015
Renewable match
80%
Rack density
5 kW
PUE
1.371.00 ideal · 1.60 typical
Power source
Toronto Hydro / Hydro One / IESO. Dual feeds plus on-site diesel. Nuclear-plus-hydro Ontario mix.

Cooling

Plant

Evaporative

Liquid

Not deployed

Rack density

5 kW

H100-eq

—

WUE

1.41 L/kWh

evaporative fleet · 2025 · 124k m³/yr at 10 MW

0 dry2.50 evaporative

Operator average for evaporative halls, applied here — not a meter on this site. Equinix 2025 Sustainability Report.

IDEC / chilled-water CRAH, N+1. Campus Cooling as a Service is available for high-density cabinets on request.

Network carriers

7

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

6

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Toronto, Ontario, Canada

Toronto, ON

43.710°, -79.390° · North America

Tenants / users

Networks, cloud, enterprise, finance — Equinix Fabric

Notes

TR4 is an Equinix IBX in the Toronto metro. Carrier-neutral IBX with Equinix Fabric, Internet Exchange, and cloud on-ramps. Fleet-average PUE was 1.37 in 2025.

Operator site

Compiled from public filings, operator pages, and reporting. Not an official operator specification.