Equinix HH1
Equinix · Hamburg
- IT live
- 8 MW
- Free to lease
- 0.8 MW
- $ / kW·mo
- $186
- White space
- 67k ft²
Inventory
90% occupiedPower
8 MWlive
0.8 MW to lease · 7.2 MW in use
White space
67k ft²total
6,667 ft² free · 60k ft² occupied
6,194 m² · 619 m² free
Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.
Power
About 2.4 MW of the utility feed is cooling, conversion, and house load.
Power cost
$186/kW·mo
18.6¢ industrial · 25.5¢ after PUE 1.37
- Per MW·year
- $2.2M
- This site · 8 MW
- $18M/yr
- 5 kW rack
- $930/mo
5.8× the cheapest market (Iceland Landsvirkjun). Same IT load there is $15M/yr less.
Germany industrial · utility tariff × PUE, not colo list price.
- Redundancy
- N+1
- Opened
- 2016
- Renewable match
- 96%
- Rack density
- 5 kW
- PUE
- 1.371.00 ideal · 1.60 typical
- Power source
- Mainova / German grid plus Equinix PPAs.
Cooling
Plant
Evaporative
Liquid
Not deployed
Rack density
5 kW
H100-eq
—
WUE
1.41 L/kWh
evaporative fleet · 2025 · 99k m³/yr at 8 MW
Operator average for evaporative halls, applied here — not a meter on this site. Equinix 2025 Sustainability Report.
IDEC / chilled-water CRAH, N+1. Campus Cooling as a Service is available for high-density cabinets on request.
Network carriers
8On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
6Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Hamburg, Hamburg, Germany
Hamburg, Germany
53.551°, 9.994° · Europe
Tenants / users
Networks, cloud, enterprise, finance — Equinix Fabric
Notes
HH1 is an Equinix IBX in the Hamburg metro. Carrier-neutral IBX with Equinix Fabric, Internet Exchange, and cloud on-ramps. Fleet-average PUE was 1.37 in 2025.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.