Data4 MAD01
Data4 · San Agustín de Guadalix
- IT live
- 12 MW
- Free to lease
- 1.7 MW
- $ / kW·mo
- $109
- White space
- 43k ft²
Inventory
86% occupiedPower
12 MWlive
1.7 MW to lease · 10.3 MW in use
White space
43k ft²total
6,000 ft² free · 37k ft² occupied
3,982 m² · 557 m² free
Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.
Power
About 48 MW of the utility feed is cooling, conversion, and house load.
Power cost
$109/kW·mo
12.2¢ industrial · 14.9¢ after PUE 1.22
- Per MW·year
- $1.3M
- This site · 12 MW
- $16M/yr
- 25 kW rack
- $2,716/mo
3.8× the cheapest market (Iceland Landsvirkjun). Same IT load there is $12M/yr less.
Spain industrial · utility tariff × PUE, not colo list price.
- Redundancy
- N+1
- Opened
- 2026
- Renewable match
- 90%
- Rack density
- 25 kW
- PUE
- 1.221.00 ideal · 1.60 typical
- Power source
- Redeia. Four-building campus to 2029.
Cooling
Plant
Hybrid
Liquid
Deployed
Rack density
25 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
First of four buildings live at 12 MW IT; campus 48 MW with liquid-ready AI halls.
Network carriers
5On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
4Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
San Agustín de Guadalix, Madrid, Spain
San Agustín de Guadalix, Madrid
40.677°, -3.615° · Europe
Tenants / users
Hyperscale, cloud
Notes
Commissioned March 2026. Full campus expected 2029.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.