CyrusOne NVA6 Sterling
CyrusOne (KKR) · Northern Virginia
- IT live
- 45 MW
- Free to lease
- 5.4 MW
- $ / kW·mo
- $68
- White space
- 235k ft²
Inventory
88% occupiedPower
45 MWlive
5.4 MW to lease · 39.6 MW in use
White space
235k ft²total
23k ft² free · 212k ft² occupied
22k m² · 2,090 m² free
Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.
Power
About 11.3 MW of the utility feed is cooling, conversion, and house load.
Power cost
$68/kW·mo
7.3¢ industrial · 9.3¢ after PUE 1.28
- Per MW·year
- $819k
- This site · 45 MW
- $37M/yr
- 20 kW rack
- $1,364/mo
2.3× the cheapest market (Iceland Landsvirkjun). Same IT load there is $21M/yr less.
Northern Virginia / Dominion · utility tariff × PUE, not colo list price.
- Redundancy
- 2N
- Opened
- 2019
- Renewable match
- 50%
- Rack density
- 20 kW
- PUE
- 1.281.00 ideal · 1.60 typical
- Power source
- Dominion Energy. Dual 34.5 kV inlets plus on-site diesel. Northern Virginia PJM.
Cooling
Plant
Hybrid
Liquid
Deployed
Rack density
20 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.
Network carriers
4On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
4Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Sterling, Virginia, United States
Sterling, VA
39.008°, -77.432° · North America
Tenants / users
Hyperscale, cloud
Notes
Pair to NVA5 on the Sterling campus. KKR/GIP wholesale, not retail IBX.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.