Compass Datacenters Leesburg
Compass Datacenters · Leesburg
- IT live
- 72 MW
- Free to lease
- 6.5 MW
- $ / kW·mo
- $67
- White space
- 180k ft²
Inventory
91% occupiedPower
72 MWlive
6.5 MW to lease · 65.5 MW in use
White space
180k ft²total
16k ft² free · 164k ft² occupied
17k m² · 1,505 m² free
Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.
Power
About 24 MW of the utility feed is cooling, conversion, and house load.
Power cost
$67/kW·mo
7.3¢ industrial · 9.1¢ after PUE 1.25
- Per MW·year
- $799k
- This site · 72 MW
- $58M/yr
- 40 kW rack
- $2,665/mo
2.3× the cheapest market (Iceland Landsvirkjun). Same IT load there is $32M/yr less.
Northern Virginia / Dominion · utility tariff × PUE, not colo list price.
- Redundancy
- 2N
- Opened
- 2021
- Renewable match
- 20%
- Rack density
- 40 kW
- PUE
- 1.251.00 ideal · 1.60 typical
- Power source
- NOVEC.
Cooling
Plant
Hybrid
Liquid
Deployed
Rack density
40 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Powered-shell hyperscale with liquid-ready manifolds.
Network carriers
5On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
4Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Leesburg, Virginia, United States
Leesburg, Loudoun County, VA
39.116°, -77.564° · North America
Tenants / users
Hyperscale
Notes
Powered-shell model: Compass delivers the building and power, the tenant fits out IT and cooling.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.