CDC Silverdale Campus One
CDC Data Centres · Silverdale
- IT live
- 22 MW
- Free to lease
- 2.6 MW
- $ / kW·mo
- $82
- White space
- 375k ft²
Inventory
88% occupiedPower
22 MWlive
2.6 MW to lease · 19.4 MW in use
White space
375k ft²total
13k ft² free · 362k ft² occupied
35k m² · 1,226 m² free
Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.
Power
About 53 MW of the utility feed is cooling, conversion, and house load.
Power cost
$82/kW·mo
9.2¢ industrial · 11.2¢ after PUE 1.22
- Per MW·year
- $983k
- This site · 22 MW
- $22M/yr
- 15 kW rack
- $1,229/mo
2.9× the cheapest market (Iceland Landsvirkjun). Same IT load there is $14M/yr less.
Vector / NZAS-linked · utility tariff × PUE, not colo list price.
- Redundancy
- N+1
- Opened
- 2022
- Renewable match
- 85%
- Rack density
- 15 kW
- PUE
- 1.221.00 ideal · 1.60 typical
- Power source
- Vector / Transpower. Dual feeds plus on-site generators. ~85 percent renewable NZ grid.
Cooling
Plant
Closed-loop liquid
Liquid
Deployed
Rack density
15 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Closed-loop liquid from commissioning. CDC reports zero freshwater towers on Auckland campuses.
Network carriers
6On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
4Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Silverdale, Auckland, New Zealand
29 Highgate Parkway, Silverdale 0932
-36.623°, 174.680° · Oceania
Tenants / users
Government, hyperscale, enterprise — NZ first hyperscale
Notes
Aotearoa's first hyperscale campus. 22 MW live, 60 MW+ design. Net-zero carbon certified from year one. Closed-loop cooling saves evaporative water on the North Shore.