Tier III

CDC Laverton Campus Two

CDC Data Centres · Melbourne West

Planned IT
300 MW
Free to lease
240 MW
$ / kW·mo
$121
White space
938k ft²

Inventory

20% occupied

Power

300 MWlive

240 MW to lease · 60 MW in use

White space

938k ft²total

750k ft² free · 188k ft² occupied

87k m² · 70k m² free

Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.

Power

IT live
Free to lease240 MW
Utility feed
Campus / planned300 MW

Power cost

$121/kW·mo

13.8¢ industrial · 16.6¢ after PUE 1.20

Per MW·year
$1.5M
This site · 300 MW
$435M/yr
30 kW rack
$3,627/mo
3.2¢ cheapdear 22.4¢

4.3× the cheapest market (Iceland Landsvirkjun). Same IT load there is $334M/yr less.

Victoria NEM · utility tariff × PUE, not colo list price.

Redundancy
N+1
Opened
2027
Renewable match
70%
Rack density
30 kW
PUE
1.201.00 ideal · 1.60 typical
Power source
Powercor. Part of 400+ MW Laverton master plan.

Cooling

Plant

Hybrid

Liquid

Deployed

Rack density

30 kW

H100-eq

WUE

Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.

Hyperscale wholesale, liquid-ready.

Network carriers

5

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

4

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Laverton North, Victoria, Australia

Laverton North, VIC

-37.840°, 144.770° · Oceania

Tenants / users

Hyperscale

Notes

300 MW under construction — among Australia's top-three active builds.