Operational
Hyperscale
Liquid cooling
Tier III

Microsoft West India Mumbai

Microsoft Azure · Mumbai Cloud Region

IT live
50 MW
Remaining
30 MW
$ / kW·mo
$88
White space
156k ft²

Inventory

63% occupied

Power

80 MWcampus

30 MW to commission · 50 MW in use

White space

250k ft²total

94k ft² free · 156k ft² occupied

23k m² · 8,710 m² free

Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.

Power

IT live50 MW
Remaining30 MW
Utility feed100 MW
Campus / planned80 MW

About 50 MW of the utility feed is cooling, conversion, and house load.

Power cost

$88/kW·mo

10.4¢ industrial · 12.1¢ after PUE 1.16

Per MW·year
$1.1M
This site · 50 MW
$53M/yr
30 kW rack
$2,642/mo
3.2¢ cheapdear 22.4¢

3.3× the cheapest market (Iceland Landsvirkjun). Same IT load there is $37M/yr less.

MSEDCL / Tata Power · utility tariff × PUE, not colo list price.

Redundancy
2N
Opened
2015
Renewable match
30%
Rack density
30 kW
PUE
1.161.00 ideal · 1.60 typical
Power source
MSEDCL / Tata Power plus on-site generators. Dual utility feeds where available.

Cooling

Plant

Hybrid

Liquid

Deployed

Rack density

30 kW

H100-eq

WUE

0.27 L/kWh

fleet avg · 2025 · 118k m³/yr at 50 MW

0 dry2.50 evaporative

Operator fleet average applied to this hall — not a site meter. Microsoft FY2025 water intensity disclosure.

Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.

Network carriers

6

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

1

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Mumbai, Maharashtra, India

Mumbai / Navi Mumbai metro

19.100°, 73.000° · Asia

Tenants / users

Azure

Notes

Azure West India. Pair regions Central (Pune) and South (Chennai).

Operator site

Compiled from public filings, operator pages, and reporting. Not an official operator specification.