AWS Clinton
Amazon Web Services · Hinds County
- Planned IT
- —
- Remaining
- —
- $ / kW·mo
- $76
- White space
- —
Power
Power cost
$76/kW·mo
8¢ industrial · 10.4¢ after PUE —
- Per MW·year
- $911k
- This site
- —
2.5× the cheapest market (Iceland Landsvirkjun).
US industrial · utility tariff × PUE, not colo list price.
- Redundancy
- —
- Opened
- —
- Renewable match
- —
- Rack density
- —
- Voltage
- —
- PUE
- —1.00 ideal · 1.60 typical
- Power source
- —
Cooling
Plant
Air / CRAH
Liquid
Not deployed
Rack density
—
H100-eq
—
WUE
0.12 L/kWh
fleet avg · 2025
Operator fleet average applied to this hall — not a site meter. AWS 2025 sustainability disclosure.
Air-cooled chillers in a retrofitted building (Amazon to Mississippi Today, Jun 2026).
Network carriers
0No on-net carriers published.
On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
1Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Clinton, Mississippi, United States
32.341°, -90.322° · North America
Tenants / users
Amazon
Notes
In site prep / pre-construction; retrofitted building (Amazon to Mississippi Today, Jun 2026). Coordinates: OSM relation 13650977 (town center, approximate). Source: https://mississippitoday.org/2026/06/09/amazon-data-centers-mississippi/
Compiled from public filings, operator pages, and reporting. Not an official operator specification.