AWS Canada West (Calgary)
Amazon Web Services · ca-west-1
- IT live
- 48 MW
- Remaining
- 32 MW
- $ / kW·mo
- $60
- White space
- 417k ft²
Inventory
60% occupiedPower
80 MWcampus
32 MW to commission · 48 MW in use
White space
694k ft²total
278k ft² free · 417k ft² occupied
65k m² · 26k m² free
Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.
Power
About 52 MW of the utility feed is cooling, conversion, and house load.
Power cost
$60/kW·mo
7.2¢ industrial · 8.3¢ after PUE 1.15
- Per MW·year
- $725k
- This site · 48 MW
- $35M/yr
- 20 kW rack
- $1,209/mo
2.3× the cheapest market (Iceland Landsvirkjun). Same IT load there is $19M/yr less.
Alberta AESO · utility tariff × PUE, not colo list price.
- Redundancy
- N+1
- Opened
- 2023
- Renewable match
- 40%
- Rack density
- 20 kW
- PUE
- 1.151.00 ideal · 1.60 typical
- Power source
- ENMAX / AESO. Dual feeds plus on-site diesel. Gas-marginal Alberta grid.
Cooling
Plant
Hybrid
Liquid
Deployed
Rack density
20 kW
H100-eq
—
WUE
0.12 L/kWh
fleet avg · 2025 · 50k m³/yr at 48 MW
Operator fleet average applied to this hall — not a site meter. AWS 2025 sustainability disclosure.
Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.
Network carriers
6On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
1Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Calgary, Alberta, Canada
Greater Calgary (AZ undisclosed)
51.050°, -114.070° · North America
Tenants / users
AWS
Notes
ca-west-1. Second AWS Canadian region. Prairie dual-site to Montréal. AESO gas-marginal — not the Hydro-Québec story.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.