Operational
Hyperscale
Liquid cooling
Tier III

AWS Asia Pacific Bangkok

Amazon Web Services · Thailand Cloud Region

IT live
32 MW
Remaining
23 MW
$ / kW·mo
$86
White space
246k ft²

Inventory

58% occupied

Power

55 MWcampus

23 MW to commission · 32 MW in use

White space

422k ft²total

177k ft² free · 246k ft² occupied

39k m² · 16k m² free

Remaining power is campus IT not yet commissioned — captive capacity, not third-party colo.

Power

IT live32 MW
Remaining23 MW
Utility feed68.8 MW
Campus / planned55 MW

About 36.8 MW of the utility feed is cooling, conversion, and house load.

Power cost

$86/kW·mo

10.2¢ industrial · 11.8¢ after PUE 1.16

Per MW·year
$1M
This site · 32 MW
$33M/yr
25 kW rack
$2,159/mo
3.2¢ cheapdear 22.4¢

3.2× the cheapest market (Iceland Landsvirkjun). Same IT load there is $23M/yr less.

EGAT / PEA · utility tariff × PUE, not colo list price.

Redundancy
N+1
Opened
2025
Renewable match
20%
Rack density
25 kW
PUE
1.161.00 ideal · 1.60 typical
Power source
MEA / PEA / EGAT. Dual feeds plus on-site generators.

Cooling

Plant

Hybrid

Liquid

Deployed

Rack density

25 kW

H100-eq

WUE

0.12 L/kWh

fleet avg · 2025 · 34k m³/yr at 32 MW

0 dry2.50 evaporative

Operator fleet average applied to this hall — not a site meter. AWS 2025 sustainability disclosure.

Hybrid CRAH plus CDU-fed direct-to-chip loops for high-density AI cabinets.

Network carriers

4

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

1

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Bangkok, Bangkok, Thailand

Bangkok metro (ap-southeast-7)

13.750°, 100.520° · Asia

Tenants / users

AWS customers

Notes

ap-southeast-7. AWS Thailand region. Three AZs.

Operator site

Compiled from public filings, operator pages, and reporting. Not an official operator specification.