AmForge Kangerlussuaq
AmForge / GreenMet · Kangerlussuaq
- Planned IT
- 300 MW
- Free to lease
- 300 MW
- $ / kW·mo
- $73
- White space
- 600k ft²
Inventory
0% occupiedPower
300 MWlive
300 MW to lease · 0 MW in use
White space
600k ft²total
600k ft² free · — occupied
56k m² · 56k m² free
Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.
Power
Power cost
$73/kW·mo
9.2¢ industrial · 9.9¢ after PUE 1.08
- Per MW·year
- $870k
- This site · 300 MW
- $261M/yr
- 80 kW rack
- $5,803/mo
2.9× the cheapest market (Iceland Landsvirkjun). Same IT load there is $170M/yr less.
Nukissiorfiit · utility tariff × PUE, not colo list price.
- Redundancy
- N+1
- Opened
- 2030
- Renewable match
- 40%
- Rack density
- 80 kW
- PUE
- 1.081.00 ideal · 1.60 typical
- Power source
- Phase 1 LNG barges; phase 2 a new hydro plant. No land or approvals secured as of 2026.
Cooling
Plant
Free air
Liquid
Deployed
Rack density
80 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Arctic free-air plus liquid-ready AI halls — on paper. Greenland's business minister has called a 2028 finish 'birds on the roof' and pointed to 2035.
Network carriers
2On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
0No public-cloud on-ramp published.
Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Kangerlussuaq, Qeqqata, Greenland
Kangerlussuaq fjord, Greenland
67.012°, -50.711° · North America
Tenants / users
Undisclosed
Notes
300 MW mid-2027 / 1.5 GW 2028 claim from AmForge. Treat as speculative pipeline: no permits, no hydro, no cable. Included because it is the only hyperscale proposal on the island.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.