Expanding
Colocation
Liquid cooling
Tier III

Aligned PHX Union Hills

Aligned Data Centers · PHX-01/02/03

IT live
120 MW
Free to lease
14.4 MW
$ / kW·mo
White space
703k ft²

Inventory

88% occupied

Power

120 MWlive

14.4 MW to lease · 106 MW in use

White space

703k ft²total

45k ft² free · 658k ft² occupied

65k m² · 4,181 m² free

Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.

Power

IT live120 MW
Free to lease14.4 MW
Utility feed225 MW
Campus / planned180 MW

About 105 MW of the utility feed is cooling, conversion, and house load.

Power cost

/kW·mo

industrial

Per MW·year
This site · 120 MW
3.2¢ cheapdear 22.4¢

Market industrial · utility tariff × PUE, not colo list price.

Redundancy
2N
Opened
2017
Renewable match
40%
Rack density
30 kW
PUE
1.151.00 ideal · 1.60 typical
Power source
APS / SRP. Dual 69 kV inlets. Desert dry-cooler campus.

Cooling

Plant

Evaporative

Liquid

Deployed

Rack density

30 kW

H100-eq

WUE

Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.

Aligned DeltaFlow near-zero-water cooling plus liquid-ready manifolds for AI cabinets.

Network carriers

4

On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.

Clouds

4

Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.

Location

Phoenix, Arizona, United States

2500 W Union Hills Drive, Phoenix, AZ

33.655°, -112.111° · North America

Tenants / users

Hyperscale, cloud, AI

Notes

55-acre Union Hills campus. Advanced Cooling Lab on site. Complements DAL-01 already in the index. Macquarie-backed.

Operator site