Aligned PDX-01 Hillsboro
Aligned Data Centers · PDX-01
- Planned IT
- 72 MW
- Free to lease
- 72 MW
- $ / kW·mo
- $47
- White space
- 225k ft²
Inventory
0% occupiedPower
72 MWlive
72 MW to lease · 0 MW in use
White space
225k ft²total
225k ft² free · — occupied
21k m² · 21k m² free
Free power is unsold critical IT at this building, not utility headroom. Space is computer-room white space.
Power
Power cost
$47/kW·mo
5.2¢ industrial · 6.5¢ after PUE 1.25
- Per MW·year
- $569k
- This site · 72 MW
- $41M/yr
- 30 kW rack
- $1,424/mo
1.6× the cheapest market (Iceland Landsvirkjun). Same IT load there is $16M/yr less.
PGE / BPA · utility tariff × PUE, not colo list price.
- Redundancy
- 2N
- Opened
- 2026
- Renewable match
- 80%
- Rack density
- 30 kW
- PUE
- 1.251.00 ideal · 1.60 typical
- Power source
- Portland General Electric / BPA. Dual feeds. Hydro-backed Northwest grid.
Cooling
Plant
Free air
Liquid
Deployed
Rack density
30 kW
H100-eq
—
WUE
—
Operator has not published WUE. Blank, not zero — air-cooled sites still use some water.
Aligned DeltaFlow near-zero-water cooling plus liquid-ready manifolds for AI cabinets.
Network carriers
4On-net and metro carriers typically present at this location, including internet exchanges. Not a full circuit inventory.
Clouds
4Native regions and typical Direct Connect / ExpressRoute / Interconnect on-ramps at this campus. Availability varies by hall.
Location
Hillsboro, Oregon, United States
Hillsboro, OR
45.534°, -122.929° · North America
Tenants / users
Hyperscale
Notes
Northwest Aligned campus. Complements QTS Hillsboro and STACK Portland already in the index. BPA-cheap power.
Compiled from public filings, operator pages, and reporting. Not an official operator specification.